Changes to some Enterprise Resource Pool fields get overwritten da

B

Barb PMO

When I save changes to various fields (Name, Group, Initials) on checked out
Enterprise resources, the changes get overwritten the next day. Other changes
(such as Std. Rate and Ovt. Rate) are fine.

I have a feeling that the changes are happening as a result of a
sychonization from Active Directory to Project Server. If that is the case,
should I be having the Name, Group and Initials fields updated in Active
Directory?

We are using Project Pro 2003 and Project Server (both up-to-date with all
the latest servces packs).
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top