S
SteveP
Note: We are using Project Server Professional 2007 SP1
We have a Template that uses the Standard (Project Calendar) which
does not allow scheduling on weekends. The Template was saved as a
Project, and when we attempt to change the calendar to "Calendar Plus
Weekends", it appears to let us do this, until we try and assign a
resource a weekend, then we receive the message to move it to the next
working day, and there is not an option to keep a Saturday or Sunday
as a work day.
Any suggestions on what we might be doing wrong?
Thanks
Steve
We have a Template that uses the Standard (Project Calendar) which
does not allow scheduling on weekends. The Template was saved as a
Project, and when we attempt to change the calendar to "Calendar Plus
Weekends", it appears to let us do this, until we try and assign a
resource a weekend, then we receive the message to move it to the next
working day, and there is not an option to keep a Saturday or Sunday
as a work day.
Any suggestions on what we might be doing wrong?
Thanks
Steve