Changing a resource's schedule

R

Richard

Hopefully this is an easy question.

If I change the working hours of a resource, say that resource wants
next Monday off, how does that propagate to any project plans the
resource is assigned to? Does it automatically change the plan or do I
need to do something manually to reflect the change in working hours in
the plan?

Thanks again,

Richard
 
G

Gérard Ducouret

Richard,
This is an easy answer : No problem.
If you set a day off in a resource calendar, all the tasks which used that
resource on this specific day will be postponed.

Gérard Ducouret
 
R

Richard

Thanks again! Maybe I'm just impatient, my server is on a workstation
and it's probably just slow in updating.
 
D

Dale Howard [MVP]

Richard --

To piggyback on Gerard's excellent answer, your project managers must
actually open any project in which the resource in question is a team member
and assigned to tasks. As they open each of these projects, the system will
actually reschedule work assigned to the resource on the day the resource is
taking a day of vacation. Hope this helps.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top