S
Shaun Wilson
I am trying to set Project up at work to use overtime and have come across a
problem. FYI, all the employees work 40 hour weeks and have overtime rates
(after the 8 hours). Overtime is a random thing though, people do it when
they need to as long as they can.
My company estimates the length of our tasks in hours(work), so to
accomodate this I have changed the project default task type to "Fixed Work".
In the Entry table I added the field Work, and we enter the estimates into
this field (instead of the duration field). The duration defaults to "1day?"
and when we assign a work resource and (it sees their calander is an 8 hour
day) the duration increases as it should. eg a 36 hour task would say "1day?"
then when we assign bob it increases to "4.5days?". This is okay (although if
there is a way for it to automatically presume 4.5 that would be good).
Moving on, as each day passes we need to enter the times everyone worked
into the Task Usage view.
At first, I tried showing the Actual Work field and adding the time into
this. This worked good for reducing the duration, but could not work out the
overtime. So in my example, bob would do 10 hours actual on day 1 and day 5
would reduce to 2 hours.
I then (using a new test project) tried using the Actual Overtime Work field
as well to get the overtime cost to calculate. I would put 8 hours in Act.
Work and then 2 hours in Act. Overtime Work. This would then update Act. Work
to 10 hours and reduce day 5 to 2 hours. The overtime cost would also be
calculated. This is all good, however if I tried changing the 2 hours
overtime to 1 hour, the Work field on the next 4 days would change to 8.3,
8.3, 8.3, 2.08. My Work for this task is still 36hours, but why is it saying
to do part hours on the other days instead of saying 8, 8, 8, 3?
I also tried (in another new test) to use the Regular Work field, as after
some googling I discovered Actual Work = Regular Work + Overtime Work.
However, this has the problem. I also noticed that on the 2nd to 4th days
(5th similar with different values), the Regular Work would say 8 whilst the
Work would be 8.3. If i changed the Work to 8, Regular Work would drop to
7.7), and the task Work would drop to 35.7.
Anyone care to shed some light? I'm thinking this might be something to do
with the resource max units % thing (which I have not touched). Also, this
does not happen if you increase the overtime.
Shaun.
problem. FYI, all the employees work 40 hour weeks and have overtime rates
(after the 8 hours). Overtime is a random thing though, people do it when
they need to as long as they can.
My company estimates the length of our tasks in hours(work), so to
accomodate this I have changed the project default task type to "Fixed Work".
In the Entry table I added the field Work, and we enter the estimates into
this field (instead of the duration field). The duration defaults to "1day?"
and when we assign a work resource and (it sees their calander is an 8 hour
day) the duration increases as it should. eg a 36 hour task would say "1day?"
then when we assign bob it increases to "4.5days?". This is okay (although if
there is a way for it to automatically presume 4.5 that would be good).
Moving on, as each day passes we need to enter the times everyone worked
into the Task Usage view.
At first, I tried showing the Actual Work field and adding the time into
this. This worked good for reducing the duration, but could not work out the
overtime. So in my example, bob would do 10 hours actual on day 1 and day 5
would reduce to 2 hours.
I then (using a new test project) tried using the Actual Overtime Work field
as well to get the overtime cost to calculate. I would put 8 hours in Act.
Work and then 2 hours in Act. Overtime Work. This would then update Act. Work
to 10 hours and reduce day 5 to 2 hours. The overtime cost would also be
calculated. This is all good, however if I tried changing the 2 hours
overtime to 1 hour, the Work field on the next 4 days would change to 8.3,
8.3, 8.3, 2.08. My Work for this task is still 36hours, but why is it saying
to do part hours on the other days instead of saying 8, 8, 8, 3?
I also tried (in another new test) to use the Regular Work field, as after
some googling I discovered Actual Work = Regular Work + Overtime Work.
However, this has the problem. I also noticed that on the 2nd to 4th days
(5th similar with different values), the Regular Work would say 8 whilst the
Work would be 8.3. If i changed the Work to 8, Regular Work would drop to
7.7), and the task Work would drop to 35.7.
Anyone care to shed some light? I'm thinking this might be something to do
with the resource max units % thing (which I have not touched). Also, this
does not happen if you increase the overtime.
Shaun.