I read through the thread, "Project Status - Archiving/Closing a Project"
because we also are looking for a way to archive projects.
I went to the referenced link,
http://www.projectserverexperts.com/Shared Documents/ArchiveCompletedProjects.htm.
I read the document titled, "How do I archive completed projects in the
production Project Server database?" I can see how this will work, however,
regarding the Note: on Step #4 below, since we are using Enterprise
Resources, I cannot change the Booking value for the team members within the
project. It comes up grayed out, as if in a read-only mode.
Am I out of luck or is there another solution for Enterprise Resources?
====================================================
Archive Completed Projects
When a project team completes a project, the project manager should
immediately do the following:
1. Open the completed project in Microsoft Project Professional
2. Click Project - Project Information, set the Production Status field
value to Completed, and then click OK
3. Click Tools - Build Team from Enterprise
4. Set the Booking value for each project team member to Proposed and
then click OK
5. Click Collaborate - Publish - All Information
6. Save and close the completed project
Note: Step #4 above is vital to the archiving process, as it will remove the
task assignments from each team member's timesheet in Project Web Access for
the completed project.
====================================================
because we also are looking for a way to archive projects.
I went to the referenced link,
http://www.projectserverexperts.com/Shared Documents/ArchiveCompletedProjects.htm.
I read the document titled, "How do I archive completed projects in the
production Project Server database?" I can see how this will work, however,
regarding the Note: on Step #4 below, since we are using Enterprise
Resources, I cannot change the Booking value for the team members within the
project. It comes up grayed out, as if in a read-only mode.
Am I out of luck or is there another solution for Enterprise Resources?
====================================================
Archive Completed Projects
When a project team completes a project, the project manager should
immediately do the following:
1. Open the completed project in Microsoft Project Professional
2. Click Project - Project Information, set the Production Status field
value to Completed, and then click OK
3. Click Tools - Build Team from Enterprise
4. Set the Booking value for each project team member to Proposed and
then click OK
5. Click Collaborate - Publish - All Information
6. Save and close the completed project
Note: Step #4 above is vital to the archiving process, as it will remove the
task assignments from each team member's timesheet in Project Web Access for
the completed project.
====================================================