Changing calculation of total cost

  • Thread starter Jumpinjackflash
  • Start date
J

Jumpinjackflash

Project seems to only allow calculating a total cost based on what is entered
in a fixed-cost per field task and other resource usage cost fields.
I need to add two custom fixed-cost fields per task (billable capital and
non-billable capital). How can I change how total cost is calculated?
 
J

Jan De Messemaeker

Hi,

Only through VBA I'm afraid. None of the cost foields can be accessed by a
formula.
HTH
 
H

hberkis

Do you have any references that would discuss what would be involved in using
VBA to change the Total Cost calculation?
 
J

John

hberkis said:
Do you have any references that would discuss what would be involved in using
VBA to change the Total Cost calculation?

hberkis,
I'm not sure what kind of references you are looking for but here are a
couple. First, if you do not have any VBA experience but are willing to
learn, go to our MVP website at: http://www.mvps.org/project/links.htm
and click on the link at the bottom of the page for, "Project 98 Visual
Basic Environment Training Materials". Even though it says it is for
Project 98, it is equally applicable to all current versions of Project.

For some good examples of VBA, try fellow MVP, Jack Dahlgren's website
at: http://masamiki.com/project/macros.htm

Beyond those, you can always post to the developer newsgroup - we
generally like to address VBA and other developer questions there.

John
Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top