Changing % complete for a task that passed its finish date

S

Samantha

In Project 2002 - I cannot change the % complete on a task that has passed
it's finish date - how can I do this?
 
M

Mike Glen

Hi Samantha ,

Welcome to this Microsoft Project newsgroup :)

You need to enter the actual data - Actual work and Remaining Work and let
Project calculate the %Complete.

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on :))

Mike Glen
MS Project MVP
 
G

Gérard Ducouret

Hello Samantha,
Have you tried to add any Remaining duration in the Update tasks dialog box
?
Tools / Tracking / Update Tasks...

Hope this helps,

Gérard Ducouret
 
S

Samantha

Thanks - I entered the same question twice (gotta get used to this method of
questioning.) It worked - thank you both.
 