A
A Nichols
I have a project I'm currently managing in project server 2003. Initially
the server was set to track progress with:
"Percent of work complete: Resources report the percent of work complete,
between 0 and 100%."
I've changed this setting to:
"Hours of work done per day or per week: Resources report the hours worked
on each task during each time period." and set the server to force project
managers to use this reporting method.
For some reason this change is not taking effect. Could this be because I
have some acutals reported in already?
the server was set to track progress with:
"Percent of work complete: Resources report the percent of work complete,
between 0 and 100%."
I've changed this setting to:
"Hours of work done per day or per week: Resources report the hours worked
on each task during each time period." and set the server to force project
managers to use this reporting method.
For some reason this change is not taking effect. Could this be because I
have some acutals reported in already?