Changing default units for work to hours in PWA

P

Pikey115

Hi, we are in the process of rolling out PWA (2007) to the teams - however
the My Tasks view seems to always display work units as days - we need this
to be hours - have tried chaneg the enterprise global defaults etc but no joy.

How can we change this ?
 
D

Dale Howard [MVP]

Pikey115 --

You need to modify the Web part for the My Tasks page to change the date
units. Hope this helps.
 