Changing Duration from days to hours?

B

BillyM

I decided to change the default duration from days to hours from
"tools/options/schedule". The Gant chart modified some of the durations to
hours, but left most of the task in their original "days". Is there some way
these can be converted?.
 
J

Jack D.

BillyM said:
I decided to change the default duration from days to hours from
"tools/options/schedule". The Gant chart modified some of the durations to
hours, but left most of the task in their original "days". Is there some
way these can be converted?.

You can convert them by retyping them.
I'm afraid there isn't a better way of doing it.

--
Please try to keep replies in this group. I do check e-mail, but only
infrequently. For Macros and other things check http://masamiki.com/project

-Jack Dahlgren, Project MVP
email: J -at- eM Vee Pee S dot COM


+++++++++++++++++++
 
G

Gérard Ducouret

Hello,
MS Project 2002 presents a VBA macro named Format_Duration which does that :
Tools / Macro / Macros...

HTH

Gérard Ducouret
 