Steve Lundwall
(I'm going to show my newbie status in spades!) Very slowly I am slowing
setting up a project for some software development. I have detailed the
Research and Planning tasks fairly well, assigned resources from the
Enterprise Resource Pool and established dependencies. I have refrained from
setting constraints except on a couple of things. For example, we had a 3
hour meeting at a specific time on one day this week that four of my
resources were involved with. So I set it up to start on a specific day at a
specific time and with a 3H duration and then assign all four resources with
100% Units and it showed 3H for each in the Task Form. It was subsequently
Published. When the first of these resources reported actuals against it in
PWA (3 hours) and sent the update it updated the Project on the Server but
it changed the duration to 8H. It actually did the same thing for a 2H
meeting that only two resources were assigned to. It also changed it to 8H.
Our Global Calendar is set for a 7.5H working day by default so I don't
think it is simply defaulting to a full day. Is this because I didn't save a
baseline prior to reporting actuals against it? Any ideas why it is changing
this 3 hour meeting to 8 hours? Thanks.
Steve
setting up a project for some software development. I have detailed the
Research and Planning tasks fairly well, assigned resources from the
Enterprise Resource Pool and established dependencies. I have refrained from
setting constraints except on a couple of things. For example, we had a 3
hour meeting at a specific time on one day this week that four of my
resources were involved with. So I set it up to start on a specific day at a
specific time and with a 3H duration and then assign all four resources with
100% Units and it showed 3H for each in the Task Form. It was subsequently
Published. When the first of these resources reported actuals against it in
PWA (3 hours) and sent the update it updated the Project on the Server but
it changed the duration to 8H. It actually did the same thing for a 2H
meeting that only two resources were assigned to. It also changed it to 8H.
Our Global Calendar is set for a 7.5H working day by default so I don't
think it is simply defaulting to a full day. Is this because I didn't save a
baseline prior to reporting actuals against it? Any ideas why it is changing
this 3 hour meeting to 8 hours? Thanks.
Steve