Changing durations display from hrs. to days

J

Joe

I took over an existing plan that had duration displayed
in hours. I wanted to chage this to the default using
days instead. I went to the options section and made the
change. The plan only changed the summary task durations
to days, the detailed task lines remain in hours format.
I can manually make the translation, but is there anyway
for it to convert from hours to days automatically?
 
M

Mike Glen

Hi Joe,

Welcome to this Microsoft Project newsgroup :)

Yes - try running Tools/Macro/Macros.../Format_Duration macro.

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on :))

Mike Glen
MS Project MVP
 