Changing Durations in microsoft project 2003

T

That''sMe

Some people have entered duation times in days, weeks, and months in a large
Microsfot Project 2003 schedule. How can I quickly standardize all of the
duration times to days? That is, how can I have Project change all activity
duration times to a common set of units, days?
 
J

JulieS

Hi That's Me,

Run the Format Duration macro.

Tools > Macro > Macros and run Format_Duration. The macro will allow
you to select the duration format you need.

--
I hope this helps. Let us know how you get along.

Julie

Visit http://project.mvps.org/ for FAQs and more information about
Microsoft Project.
 