B
bgriffwork
In our implementation of Project Server, we default our activities to Fixed
Duration/Effort-driven off. In several cases, we have seen Duration
increased dramitically (for example, Duration was originally 3 months, and it
gets increased to 6 months), and scheduled work spread evenly over the
increase duration. Has anyone else seen behavior like this that was casued
by Project Server? We have not been able to determine if this is being
caused by our users, something in our setup, a bug, or some other reason.
By the way, we are running Project Pro 2003 SP1. Our internal systems group
and some consultants have also not been able to explain this behavior, and
they suggest that SP2 could solve this problem.
Duration/Effort-driven off. In several cases, we have seen Duration
increased dramitically (for example, Duration was originally 3 months, and it
gets increased to 6 months), and scheduled work spread evenly over the
increase duration. Has anyone else seen behavior like this that was casued
by Project Server? We have not been able to determine if this is being
caused by our users, something in our setup, a bug, or some other reason.
By the way, we are running Project Pro 2003 SP1. Our internal systems group
and some consultants have also not been able to explain this behavior, and
they suggest that SP2 could solve this problem.