J
jpas1954
I have a user who is running Project 2000. She has all fixed duration tasks,
each showing duration and effort. She wants to change only duration. When she
does, it changes the effort. When she manually changes the effort, it flips
back to the original duration. So she can't make any changes. She sent me her
schedule. I am running 2003 and it warns me, then allows me to make these
changes. Is it her version or is it something in her setup that governs this?
each showing duration and effort. She wants to change only duration. When she
does, it changes the effort. When she manually changes the effort, it flips
back to the original duration. So she can't make any changes. She sent me her
schedule. I am running 2003 and it warns me, then allows me to make these
changes. Is it her version or is it something in her setup that governs this?