Dan Keen

I have a project plan that has both Enterprise and Local Resources. (I'm
using the Local Resources to track time/cost information for contractors
working on this project only.) It appears that one of the local resources
was accidentally imported as an enterprise resource, and I cannot find a
clean way to reverse the process. Task assignments still show up in the
project plan, but they do not appear in the resource's PWA / Tasks view.

Is there any way to back out of this mistake without creating a new local
resource and re-assigning all of the remaining work? Obviously, I want to
try to preserve all of the actual work that's already been entered.

Thanks in advance.
 
D

Dale Howard [MVP]

Dan --

Your Project Server administrator should do the following:

1. Log into PWA with administrator permissions
2. Click Admin - Clean up Project Server datbase
3. Select the resource in question
4. Click the Delete button

When your Project Server administrator performs the above actions, the
following will occur:

- The resource will be deleted from the Enterprise Resource Pool
- The resource's user account in PWA will be deleted
- In any projects to which the resource is assigned, the resource will be
converted to a local resource (without losing assignments or actuals)

At this point, you should do the following:

1. Open a project in which the resource is assigned tasks
2. Apply the Resource Sheet view
3. Remove the appended deletion comment from the local resource's name
4. Double-click the name of the local resource
5. Set the Workgroup value for this resource to None
6. Click OK
7. Save, publish, and close the project

Hope this helps.
 
D

Dan Keen

Dale -

Thanks. That did the trick.

Dan


Dale Howard said:
Dan --

Your Project Server administrator should do the following:

1. Log into PWA with administrator permissions
2. Click Admin - Clean up Project Server datbase
3. Select the resource in question
4. Click the Delete button

When your Project Server administrator performs the above actions, the
following will occur:

- The resource will be deleted from the Enterprise Resource Pool
- The resource's user account in PWA will be deleted
- In any projects to which the resource is assigned, the resource will be
converted to a local resource (without losing assignments or actuals)

At this point, you should do the following:

1. Open a project in which the resource is assigned tasks
2. Apply the Resource Sheet view
3. Remove the appended deletion comment from the local resource's name
4. Double-click the name of the local resource
5. Set the Workgroup value for this resource to None
6. Click OK
7. Save, publish, and close the project

Hope this helps.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top