Changing finish date according to a custom work field

E

ein

Hi, I'm using project server2003.
I want to change the finish date of a task according to a custom work field.

The custom work field will show the changes in work based on delayes (the
resource in not working full capacity)
I don'e want to change the work since the effort has not been changed.

How can I do this?

Ein
 
D

Dale Howard [MVP]

Ein --

The only way to change the Finish date of a task according to a custom work
field is using VBA. You might want to post this message in the
microsoft.public.project.developer newsgroup to let our developers share
their wisdom with you. Hope this helps.
 
D

Dale Howard [MVP]

Ein --

Assuming you are using the Web interface to access the newsgroups, the link
is Microsoft Project > Developer. If you are using a newsgroup reader, then
the newsgroup name is microsoft.public.project.developer. Hope this helps.
 