I inherited the Project Server and am trying to change the holiday
dates (non-working days) for 2009. I finally found where to get to
the calendar, and also found where to change the working time for a
particular date, but the From and To fields are greyed out and cannot
be changed. I do have administrator privileges to Project.

Any help is greatly appreciated.
 
S

Sean Hanson

You are using Project Server 2003, Tools Change Working Time, but did you do
this in the Enterprise Global, Tools, Enterprise Options, Open Enterprise
Global.
--
Sean Hanson

http://www.randsmanagement.com
Mass Resource Tool for 2007
Project Server 2007 Archive Tool
SRS Reports
 
M

Matt

I'm not sure what I was doing wrong the first time but I did it again
and was able to make the necessary adjustments.

Thanks,
 
C

caz4562000

I'm not sure what I was doing wrong the first time but I did it again
and was able to make the necessary adjustments.

Thanks,





- Show quoted text -

Hi,
I'm trying to also get this working. The base calender has been
changed correctly as some of our holidays for 2009 were on the wrong
days. But unfortunately I can't now see those changes in the project
calenders, they are still using the old dates. When I go to project
information there is only one possible project calender (standard)
which is selected.
I have noticed some other problems with project calenders not properly
matching the enterprise calender for hours of work per day and start
and finish times. We are using Project 2007 with Project Server. Is
there some setting I need to force all projects to use the enterprise
calender?

Caroline
 
L

L8rdays

HI Caroline,

If you only want to use the enterprise calendar make sure your PWA settings
aren't set to use individual project calendars.
 
C

caz4562000

HI Caroline,

If you only want to use the enterprise calendar make sure your PWA settings
aren't set to use individual project calendars.  







- Show quoted text -

I've had a look but I can't see where to set that option, is it in
server settings somewhere?
 
L

L8rdays

Hi Caroline,

No problem, I actually told you the wrong area. It is in the Additional
Server Settings. Second box down.

Allow projects to use local base calendars. You want to uncheck that if
you only want the users to use the enterprise calendar.

Hope that helps!
 
C

caz4562000

Hi Caroline,

No problem, I actually told you the wrong area.  It is in the Additional
Server Settings.  Second box down.

Allow projects to use local base calendars.   You want to uncheck that if
you only want the users to use the enterprise calendar.

Hope that helps!






- Show quoted text -

Thanks, found it and it is not allowing local calenders as you
suggest.
Actually I got the public holiday issue fixed now by editing from
server settings not from MS project.
And so far the projects seem to have the right calenders, I'll have to
keep monitoring it.

Caroline
 
G

Gary L. Chefetz

In 2007, you must always start your calendar edits from PWA. This is a new
behavior in 2007.

--
----------
Gary L. Chefetz, MVP
MSProjectExperts
Project Server Consulting: http://www.msprojectexperts.com
Project Server Training: http://www.projectservertraining.com
Project Server FAQS: http://www.projectserverexperts.com
Project Server Help Blog: http://www.projectserverhelp.com


Hi Caroline,

No problem, I actually told you the wrong area. It is in the Additional
Server Settings. Second box down.

Allow projects to use local base calendars. You want to uncheck that if
you only want the users to use the enterprise calendar.

Hope that helps!






- Show quoted text -

Thanks, found it and it is not allowing local calenders as you
suggest.
Actually I got the public holiday issue fixed now by editing from
server settings not from MS project.
And so far the projects seem to have the right calenders, I'll have to
keep monitoring it.

Caroline
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top