S
Sathish
Hi,
I'm using MS Project 2003. I've a requirement in my work that requires me
to change the working hours for the resources to 9 hours. Once I do this
change and add new tasks, the duration of the task is reflected properly by
taking into account 9 hrs per day instead of the default 8 hrs per day.
BUt the Finish date for the task is still calculated using 8 hrs per day.
This is leading to lot of Schedule Variance, which is actually not there.
Any help in this regard is greatly appreciated.
Thanks,
Sathish
I'm using MS Project 2003. I've a requirement in my work that requires me
to change the working hours for the resources to 9 hours. Once I do this
change and add new tasks, the duration of the task is reflected properly by
taking into account 9 hrs per day instead of the default 8 hrs per day.
BUt the Finish date for the task is still calculated using 8 hrs per day.
This is leading to lot of Schedule Variance, which is actually not there.
Any help in this regard is greatly appreciated.
Thanks,
Sathish