J
Jim Stoaks
When the resources were originally assigned the max units were at 100% in the
resource pool. This was changed to 80% in the pool and was picked up in the
schedule. However, when you relevel the project it gives you an error
message stating that you need to skip that task and lower the allocation for
that resource. I believe it is saying that you originally allocated the
resource at 100% and now you can allocate the resource at no more than 80%.
The correction to the problem seems to be reselecting the resource assigned
to the task which resets the allocation to 100%.
For a large project when a single person has 100's of assignments is there a
better way to do this?
Thanks,
Jim
resource pool. This was changed to 80% in the pool and was picked up in the
schedule. However, when you relevel the project it gives you an error
message stating that you need to skip that task and lower the allocation for
that resource. I believe it is saying that you originally allocated the
resource at 100% and now you can allocate the resource at no more than 80%.
The correction to the problem seems to be reselecting the resource assigned
to the task which resets the allocation to 100%.
For a large project when a single person has 100's of assignments is there a
better way to do this?
Thanks,
Jim