Changing Min/Max Project Start/Finish Dates

R

Rock

What do I need to do to enter project start and/or finish
dates before 1/1/1984?

Out of the box, project start/finish dates must be
between 1/1/1984 and 12/31/2049.

Thx
R
 
S

Steve House

The "zero date" of the date/time system Project uses internally is 1/1/84
and there's no way to enter dates earlier than that. Likewise, 2049 is when
it overflows and rolls back to zero again. Sorry about that
 
J

Jack D.

Rock said:
What do I need to do to enter project start and/or finish
dates before 1/1/1984?

Out of the box, project start/finish dates must be
between 1/1/1984 and 12/31/2049.

Thx
R

A time travel machine. What is it you are planning to do before 1984?
Unfortunately Project can not help you in this endeavor as the dates are
hard limits.


--
Please try to keep replies in this group. I do check e-mail, but only
infrequently. For Macros and other things check http://masamiki.com/project

-Jack Dahlgren, Project MVP


+++++++++++++++++++
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top