Changing of Remaining Work

J

Joerg Schrocke

Hello!

In WebAccess, we have disabled that the users can change their Remaining
Work.
Is there a possibility that only the Project Managers can update the
Remaining Work for the users.

Under Adjust Actuals you can only change the acuals. I would be great, if we
could also change the Remaining Work.

Many thanks,

Joerg
 
D

Dale Howard [MVP]

Joerg --

The project managers will need to do this in the actual Microsoft Project
plan. One way to do this is to select the task in question in the Gantt
Chart view, then click Window - Split to apply the Task Entry view. In the
Task Form (lower pane), right-click and select the Resource Work details
from the shortcut menu. In the Task Form, the project manager can now see
the Remaining Work for each resource and can adjust each accordingly. After
doing so, the project manager will then need to publish the latest schedule
changes. Hope this helps.
 
J

Joerg Schrocke

Ok, this would be an option, but the best would be if only the Project
Manager can change the Remaining Work in WebAccess.

Thanks

Joerg
 