Hi,

I just couldn't locate the steps on how to change the progress report method
for a project in Project Server 2003 if we set the "Allow project manager to
change the default method for reporting progress if a different method is
appropriate for a specific project" in the lock down defaults tracking
settings.

Any clues??? Thanks.
 
D

Dale Howard [MVP]

godrid --

The PM must open the project and click Tools - Customize - Published Fields.
The three tracking methods are listed at the top of the Published Fields
dialog. Hope this helps.
 