B
breynold55
We have a schedule that was started using an 8 hour calendar and we
are midway through the schedule, due to a change in business we want
to change the project calendar to a 6 hour day, and change the
resource Max Units to 75% in ERP. Is this possible? And, if it is,
what are the pitfalls, e.g., started tasks?
are midway through the schedule, due to a change in business we want
to change the project calendar to a 6 hour day, and change the
resource Max Units to 75% in ERP. Is this possible? And, if it is,
what are the pitfalls, e.g., started tasks?