A
Adam Bennett
Has anybody noticed an issue with the actual work recorded against a project
changing when the remaining duration is changed?
Here's the scenario we've encountered:
The project plan is setup and baselined and actual work gets applied to the
project (we're using non-managed time and tasks are typically setup as fixed
duration - effort driven). After the project has been finished, we want to
"close out" the project by changing some of the meta data fields and marking
all tasks 100% complete.
To mark the tasks 100% complete, we've been changing any remaining work that
still exists on the project down to zero. However, not all tasks are marked
at 100% with this method, so we were also changing the remaining duration
down to zero as well. When doing this though, we noticed that some actuals
are changing.
I was just curious if this was an identified issue and/or what is the best
practice for marking tasks as 100% when using non-managed time.
Thanks for the help!
Adam
changing when the remaining duration is changed?
Here's the scenario we've encountered:
The project plan is setup and baselined and actual work gets applied to the
project (we're using non-managed time and tasks are typically setup as fixed
duration - effort driven). After the project has been finished, we want to
"close out" the project by changing some of the meta data fields and marking
all tasks 100% complete.
To mark the tasks 100% complete, we've been changing any remaining work that
still exists on the project down to zero. However, not all tasks are marked
at 100% with this method, so we were also changing the remaining duration
down to zero as well. When doing this though, we noticed that some actuals
are changing.
I was just curious if this was an identified issue and/or what is the best
practice for marking tasks as 100% when using non-managed time.
Thanks for the help!
Adam