servdeproject
I have a task that is 5 days long with a no. of resources assigned to it.
resource 2 will be allocated 100% for the last 2 days, but for the first 2
days can only be allocated at 10% because they are already allocated the
remaining 90% to another project. Is there a way this variance can be
specified within the task?