Changing Resource allocation within a task.

S

servdeproject

I have a task that is 5 days long with a no. of resources assigned to it.
resource 2 will be allocated 100% for the last 2 days, but for the first 2
days can only be allocated at 10% because they are already allocated the
remaining 90% to another project. Is there a way this variance can be
specified within the task?
 
R

Reid McTaggart

In the Task Usage view of Project Pro you can adjust the planned work for
that resource on that task day by day.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top