Hi !!
I'm trying to modify the calendar of a global resource (working/non working
days) directly in Project's db, because I read that PDS doesn't support this
functionallity.
When I make some changes into a resource's calendar, I don't see any changes
in the calendar tables (MSP_CALENDARS, MSP_CALENDAR_DATA).
Is it possible to make changes into a global resource calendar without using
Project Professional ??
Thank you for your answers and sorry for my english, I'm spanish.
I'm trying to modify the calendar of a global resource (working/non working
days) directly in Project's db, because I read that PDS doesn't support this
functionallity.
When I make some changes into a resource's calendar, I don't see any changes
in the calendar tables (MSP_CALENDARS, MSP_CALENDAR_DATA).
Is it possible to make changes into a global resource calendar without using
Project Professional ??