Changing Resource Calendars

D

Debbie P

We would like our project managers to have the ability to change workdays in
their resource's standard calendars for such things as vacation, leave of
absence, etc. We don't, however, want them to be able to change any other
information in the enterprise resource pool. Is there a way to do this?
 
D

Dale Howard [MVP]

Debbie P --

No, there is no way to give your PM's access to change only part of the
resource information in the Enterprise Resource Pool. If they can open the
Enterprise Resource Pool Read/Write, they can change any information about
any resource. Hope this helps.
 
D

Debbie P

Thank you Dale, it confirmed the research and testing I had done. Just
wanted to be sure I had not missed anything.
--
Debbie P



Dale Howard said:
Debbie P --

No, there is no way to give your PM's access to change only part of the
resource information in the Enterprise Resource Pool. If they can open the
Enterprise Resource Pool Read/Write, they can change any information about
any resource. Hope this helps.
 
D

Dale Howard [MVP]

Debbie P --

Doesn't it make you feel good that an "authority" confirmed your research
and testing? HA! :) Trust your instincts, my friend; you are on the right
track!




Debbie P said:
Thank you Dale, it confirmed the research and testing I had done. Just
wanted to be sure I had not missed anything.
 