P
Peter Rooney
I have recently spent a lot of time setting the start and end times (as
against dates) of tasks in my departmental project plan to match our working
day (09:00 to 13:00 and 14:00 to 17:30 - 7.5 hours) by setting the format of
the start and end dates to display the times too, then manually changing them
(multiple raised eyebrows andglances to heaven from worldwide project users -
yes, I KNOW!)
Our working time on the standard calendar was originally 08:00 to 12:00 and
13:00-17:00, giving a working day of 8 hours, which was incorrect.
I have modified the Standard calendar to reflect these times, and ensured
that all resource calendars match them too, at least for the periods in
question, but set the tasks to ignore resource calendars anyway (who's been
reading his manuals, then?)
However, when I filter my plan and copy the filtered data to a new plan,
some of the start and end times change e.g. Start Date of 03/12/04 09:00
becomes 013/12/04 14:30. In fairness, most of the timesdon't change, which
makes it all the more puzzling - I would have expected them to be all right,
or all wrong...
The calendar assignations for the "corrupted" tasks in the new plan are the
same, and as far as I can see, nothing else has changed.
Does anybody out there have any suggestions as to what could be causing
this? I've spent a lot of time writing VBA to extract filtered areas of my
plan (specific projects, teams and resources) to seperate plan files which
can then be emailed, but if my extracts show different data, then it's not
going to be viable.
Cheers
Pete
against dates) of tasks in my departmental project plan to match our working
day (09:00 to 13:00 and 14:00 to 17:30 - 7.5 hours) by setting the format of
the start and end dates to display the times too, then manually changing them
(multiple raised eyebrows andglances to heaven from worldwide project users -
yes, I KNOW!)
Our working time on the standard calendar was originally 08:00 to 12:00 and
13:00-17:00, giving a working day of 8 hours, which was incorrect.
I have modified the Standard calendar to reflect these times, and ensured
that all resource calendars match them too, at least for the periods in
question, but set the tasks to ignore resource calendars anyway (who's been
reading his manuals, then?)
However, when I filter my plan and copy the filtered data to a new plan,
some of the start and end times change e.g. Start Date of 03/12/04 09:00
becomes 013/12/04 14:30. In fairness, most of the timesdon't change, which
makes it all the more puzzling - I would have expected them to be all right,
or all wrong...
The calendar assignations for the "corrupted" tasks in the new plan are the
same, and as far as I can see, nothing else has changed.
Does anybody out there have any suggestions as to what could be causing
this? I've spent a lot of time writing VBA to extract filtered areas of my
plan (specific projects, teams and resources) to seperate plan files which
can then be emailed, but if my extracts show different data, then it's not
going to be viable.
Cheers
Pete