J
Jane Sherman
I am using MS Project as a Resource Planning tool. I
enter a task and then use the Resource Usage sheet to
enter specific time per week for the person on the task.
If I adjust the Start Date on the Task Sheet, it "re-
levels" the time on the Resource Usage sheet. I'd really
like it to shift the time down, not re-level.
For example,
I enter a task, Task 1, duration of two weeks, Work for 3
days (I know the person is going to spend 3 days over the
next 2 weeks on the task) and it's assigned to Resource 1.
Go into the usage sheet and actually enter 3 days during
those 2 weeks.
Then go back to the task sheet and change the start
date. Go back to the usage sheet. It's leveled all of
that time again and I have to re-enter the 3 specific days.
enter a task and then use the Resource Usage sheet to
enter specific time per week for the person on the task.
If I adjust the Start Date on the Task Sheet, it "re-
levels" the time on the Resource Usage sheet. I'd really
like it to shift the time down, not re-level.
For example,
I enter a task, Task 1, duration of two weeks, Work for 3
days (I know the person is going to spend 3 days over the
next 2 weeks on the task) and it's assigned to Resource 1.
Go into the usage sheet and actually enter 3 days during
those 2 weeks.
Then go back to the task sheet and change the start
date. Go back to the usage sheet. It's leveled all of
that time again and I have to re-enter the 3 specific days.