Changing Start & Finish Dates

C

cherylsplace

I have Microsoft Projct 2007. I have a standard project plan that I us
over and over for different clients. When I "Save As" a new plan fo
a new client I need to change the start and finish dates to reflect th
current date - but it only shows the original dates when the plan wa
1st created.

So the 1st overall task I can't change, which obviously affects th
entire plan. When I go to task information these items are greyed out.
Even though I went to "Adjust dates" I put in today's date, but it i
not reflected anywhere and it did not change the initial start date.
Please help. I do not want to have to retype the same plan everytime
get a new customer.

In the image - it is the 1st line that needs to change

+-------------------------------------------------------------------
|Filename: project start date.jpg
|Download: http://forums.techarena.in/attachment.php?attachmentid=10597
+-------------------------------------------------------------------
 
R

Rod Gill

The first line is a summary task, so you really need to change Task 3: the
first sub-task. Task 3 is complete, so after saving a copy of the file the
first thing to do is select all tasks then click the 0% icon in the Track
toolbar or enter 0% in the Task information dialog. Project never moves
completed tasks.

Under Project, Properties enter your new Project Start date and provided all
tasks are linked you're good to go!

--

Rod Gill
Microsoft MVP for Project - http://www.project-systems.co.nz

Author of the only book on Project VBA, see: http://www.projectvbabook.com




cherylsplace said:
I have Microsoft Projct 2007. I have a standard project plan that I use
over and over for different clients. When I "Save As" a new plan for
a new client I need to change the start and finish dates to reflect the
current date - but it only shows the original dates when the plan was
1st created.

So the 1st overall task I can't change, which obviously affects the
entire plan. When I go to task information these items are greyed out.
Even though I went to "Adjust dates" I put in today's date, but it is
not reflected anywhere and it did not change the initial start date.
Please help. I do not want to have to retype the same plan everytime I
get a new customer.

In the image - it is the 1st line that needs to change.


+-------------------------------------------------------------------+
|Filename: project start date.jpg |
|Download: http://forums.techarena.in/attachment.php?attachmentid=10597|
+-------------------------------------------------------------------+

--
cherylsplace
------------------------------------------------------------------------
cherylsplace's Profile: http://forums.techarena.in/members/175555.htm
View this thread: http://forums.techarena.in/microsoft-project/1294102.htm

http://forums.techarena.in


__________ Information from ESET Smart Security, version of virus
signature database 4784 (20100118) __________

The message was checked by ESET Smart Security.

http://www.eset.com

__________ Information from ESET Smart Security, version of virus signature database 4784 (20100118) __________

The message was checked by ESET Smart Security.

http://www.eset.com
 
J

Jan De Messemaeker

Hi,

Select all tasks
On the toolbar click the Task Information button
General Tab
Enter 0 as %complete
OK
Now it will worlk allright
(Actual dates are never moved by Project, History is history)

HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 