A
Anthony
I made some changes to a task and now my views show some weird things. Here
is what happenend:
Task A:
John: Baseline 20h, Work 20h, Actual 10h, Remaining 10h
Mike: Baseline 20h, Work 20, Actual: 20, Remaining 0h
Total: Baseline 40h, Work 40h, Actual: 30, Remaining 10h
I then added an additional person to take over John's remaining time, but
when I look at the view (which is grouped by Task name, then resource), it
shows this:
Task A:
John: Baseline 20h, Work 10h, Actual 10h, Remaining 0h
John: Baseline 20h, Work 20h, Actual 10h, Remaining 10h
Mike: Baseline 20h, Work 20h, Actual: 20h, Remaining 0h
Mike: Baseline 20h, Work 20h, Actual: 20h, Remaining 0h
Joe: Baseline 0h, Work 10h, Actual: 0h, Remaining 10h
Total: Baseline 80h, Work 80h, Actual: 60h, Remaining 20h
In the actual project plan, it looks fine and the hours are correct, but
some of the leads are using a custom project view to look at the Task work
and the hours dont add up right. How can I fix this?
Thanks!
is what happenend:
Task A:
John: Baseline 20h, Work 20h, Actual 10h, Remaining 10h
Mike: Baseline 20h, Work 20, Actual: 20, Remaining 0h
Total: Baseline 40h, Work 40h, Actual: 30, Remaining 10h
I then added an additional person to take over John's remaining time, but
when I look at the view (which is grouped by Task name, then resource), it
shows this:
Task A:
John: Baseline 20h, Work 10h, Actual 10h, Remaining 0h
John: Baseline 20h, Work 20h, Actual 10h, Remaining 10h
Mike: Baseline 20h, Work 20h, Actual: 20h, Remaining 0h
Mike: Baseline 20h, Work 20h, Actual: 20h, Remaining 0h
Joe: Baseline 0h, Work 10h, Actual: 0h, Remaining 10h
Total: Baseline 80h, Work 80h, Actual: 60h, Remaining 20h
In the actual project plan, it looks fine and the hours are correct, but
some of the leads are using a custom project view to look at the Task work
and the hours dont add up right. How can I fix this?
Thanks!