I have a project where the PM has changed the task type to predominantly
Fixed Duration in an environment with managed time periods. This has created
a problem with some of the tasks, resource units, and has shot the finish
date out tremendously. I would like to change all of the tasks back to the
default Fixed Units. Can I do this with a project that already has actuals?
What steps would I need to take?
thanks,
Victoria