We have just started using Project Server integrated to a third party time
accounting system. Proejct managers accept time from resources through the
PWA Update page. How do I modify this view? We ned to rearrange the columns
to avoid constant scrolling to see the resource names. I have not been able
to find the realted view in the view list in the PWA Manage Views page.
 
G

Gaurav Wason

You cannot change the default view of updates. But you sure can train
managers to use groups options that does stores for future.