J
John Cello
We are currently running ProjectServer 2003, with the
Tracking Settings set to "Hours of work done per day or
per week: Resources report the hours worked on each task
during each time period." Our project managers have
expressed a desire to have their resources use
the "Percent of work complete: Resources report the
percent of work complete, between 0 and 100% reporting"
option.
Are there any ramifications in making this switch if
projects have tasks that currently have progress reported
against them in hours? I realize its a simple change to
make, but being a Microsoft product, the simple changes
can often wreak havoc.
Thanks in advance.
John Cello
John Cello Consulting
Communications For Business
www.johncelloconsulting.com
Tracking Settings set to "Hours of work done per day or
per week: Resources report the hours worked on each task
during each time period." Our project managers have
expressed a desire to have their resources use
the "Percent of work complete: Resources report the
percent of work complete, between 0 and 100% reporting"
option.
Are there any ramifications in making this switch if
projects have tasks that currently have progress reported
against them in hours? I realize its a simple change to
make, but being a Microsoft product, the simple changes
can often wreak havoc.
Thanks in advance.
John Cello
John Cello Consulting
Communications For Business
www.johncelloconsulting.com