C
Colonel Blip
I publish a weekly newsletter that has a date of publication at the first of
the newsletter. I have other sections in the newsletter that have different
dates that are respectively either 4 or 7 days later than the publication. I
would like to only have to change the 'master' date and have the rest change
to reflect it is one week later rather than manually changing these (which I
forget to do too often). Is there a way to do this in word without a macro?
If not, is there a way with vba code?
the newsletter. I have other sections in the newsletter that have different
dates that are respectively either 4 or 7 days later than the publication. I
would like to only have to change the 'master' date and have the rest change
to reflect it is one week later rather than manually changing these (which I
forget to do too often). Is there a way to do this in word without a macro?
If not, is there a way with vba code?