Changing work days/week from 5 to 4...

H

Houman Yahyaei

Question : I'm doing a project plan for a client and I need to change the
work week from 5 to 4 days, is there a way to tell it not to consider a
day/week as being available for projects, or extend the weekend to 3 days...
I need to remove Fridays from the work calendar...

I have to submit this soon and was wondering...

I'm using project 2002

Thanks very much
 
M

Mike Glen

Hi Houman,

Welcome to this Microsoft Project newsgroup :)

You need to set up a working time calendar for your project . I've
explained this in detail in my series of Microsoft Project lessons in the
TechTrax ezine, particularly Lesson 12 - Working Patterns - at this site:
http://tinyurl.com/2xbhc (Perhaps you'd care to rate it before leaving the
site, :) Thanks.)

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
 