On the Resource Usage report, the units are all reported in hours. It would
be very helpful if these could be displayed and printed in "person" units
corresponding to the column unit of measure (i.e. week, day, month, etc.).

Is there an easy way to do this? (I've been able to create customized data
columns that show the summarized values left of the data-table area, but
haven't found a way to change the table units themselves."

Thanks for any help,
 
G

Gérard Ducouret

Doug,
Have you tried :
Tools / Options / Schedule / Work is entered in... Days

Gérard Ducouret
 
J

Jan De Messemaeker

Hi, I can do it on the Resource Usage view:
Format, Detail Styles, PercentAllocation, Show
But I never use the reports, sorry.