H
hany
I have a task set up as fixed work and effort driven.
Its set up to 40 hours work.
When assigning one resource to 100 % everything is ok.
The duration i set up to 40 h.
When changing the allocation to 80 % the duration is set
to 50 h. So far so good.
After this I assign one additional resource and set that
one and the previous to 50 %.
Now the duration is set to 49.23 hours. The work still is
40 h.
I don´t understand this calculation. Anyone else who does.
Its set up to 40 hours work.
When assigning one resource to 100 % everything is ok.
The duration i set up to 40 h.
When changing the allocation to 80 % the duration is set
to 50 h. So far so good.
After this I assign one additional resource and set that
one and the previous to 50 %.
Now the duration is set to 49.23 hours. The work still is
40 h.
I don´t understand this calculation. Anyone else who does.