T
Tom C.
I'd like to set Project to schedule only 7 hours per day instead of the
default 8. I've gone into Options, Calendar and changed the workday to 9-5
from 8-5. I've indicated that the workday is only 7 days long and there are
35 hours per week.
In "Change Working Time" I tried to change the times it schedules from 8-12,
1-5 to 9-12, 1-5. However, then it marks that day as a non-default working
day. I don't really want to do this for every day in the calendar.
How do I go about changing the "default" to be 7 hours per day, so that when
I use "Change Working Time" the default is set to be only 7 hours per day,
9-12 and 1-5? I don't see any way to have those hours to be considered the
default.
I don't want to create a new calendar. I want to change the "Standard"
calendar to be only 35 hours per week. Can I do this and how?
I'm trying to make these changes in the Enterprise Global Template so all
new projects will use this new calendar.
default 8. I've gone into Options, Calendar and changed the workday to 9-5
from 8-5. I've indicated that the workday is only 7 days long and there are
35 hours per week.
In "Change Working Time" I tried to change the times it schedules from 8-12,
1-5 to 9-12, 1-5. However, then it marks that day as a non-default working
day. I don't really want to do this for every day in the calendar.
How do I go about changing the "default" to be 7 hours per day, so that when
I use "Change Working Time" the default is set to be only 7 hours per day,
9-12 and 1-5? I don't see any way to have those hours to be considered the
default.
I don't want to create a new calendar. I want to change the "Standard"
calendar to be only 35 hours per week. Can I do this and how?
I'm trying to make these changes in the Enterprise Global Template so all
new projects will use this new calendar.