S
Steve
My company has cut back the number of hours our employees work in a day from
9 to 8. I wanted to change my schedule to reflect this, but if I do, all the
durations change. I know I can add a new calendar to any new project, but
what of those projects which started during the 9 hour days and are as of yet
incomplete and will continue into the 8 hour days. When I change the hours
per day option, any 9 hour day duration adjusts the entire task to the new 8
hour day from the begining. Is there another way around this?
Project 2007 Sp2 if that helps.
9 to 8. I wanted to change my schedule to reflect this, but if I do, all the
durations change. I know I can add a new calendar to any new project, but
what of those projects which started during the 9 hour days and are as of yet
incomplete and will continue into the 8 hour days. When I change the hours
per day option, any 9 hour day duration adjusts the entire task to the new 8
hour day from the begining. Is there another way around this?
Project 2007 Sp2 if that helps.