I'm using Project 2007 and have come across a quirk that I haven't ha
on any of the previous versions.
I have altered working time for various resources (in a consoldiate
project) all seems okay when I save down but if I go back into thi
resource a few days later all the amendements I have made have bee
lost.

Can anyone help with solution to get around this?

I have been using Project for several year and doen this with all th
other versions sucessfully.
Thanks
S
 
J

JulieS

Hello Sarahjw,

When you set the share between the resource pool file and the sharer file,
did you select the option "On conflict with calendar or resource information"
to "pool takes precedence"? It's possible that the change in calendar is
being "undone" by one of the sharer files if the option is set to "sharer
takes precedence."

I hope this helps. Let us know how you get along.