J
joe
I am trying to set up a schedule where everyone is working 5 days/week, 8 hours/day for the design phase. When we go to the construction phase I want to go to a 6 days/week, 12 hours/day.
The problem is that when I put in the information and work with the durations to get the start and finish days that I want the program is telling me that I have 82 days between February 2 and April 5, even though I have changed the working times on the Standard(Project Schedule) to 6 (12 hour) days for the time framer in question
If I change the general settings under Tools/Options/Calendar to use the 6 (12 hour) days, then the design phase of my schedule has 43 days between October 2 and December 31.
Is there any way to set this up so that the duration time logically matches the start and finish dates?
The problem is that when I put in the information and work with the durations to get the start and finish days that I want the program is telling me that I have 82 days between February 2 and April 5, even though I have changed the working times on the Standard(Project Schedule) to 6 (12 hour) days for the time framer in question
If I change the general settings under Tools/Options/Calendar to use the 6 (12 hour) days, then the design phase of my schedule has 43 days between October 2 and December 31.
Is there any way to set this up so that the duration time logically matches the start and finish dates?