A
Akram Najjar
An earlier post came close to answering but did not. (7/39/3009)
Situation: an engineer works on a task for 8 days. This means sometimes
there is one interim weekend and sometimes there may be two, depending on the
starting day of the week.
Problem: This task has to be charged 8+2 or 8+4 hotel nights.
I tried creating a material or a cost Task and could not do it. They don't
have calendars. By creating a special calendar to include weekends as working
days, the engineer gets charge 16 hours for the weekend which is not the
case. Also, by creating a Hammock task across the 8 days, material got
charged on working days. If I tried elapsed time (with or without the
Hammock) everything goes crazy.
I am left with entering the nights by hand which is silly. I want it to
automatically find out whether it is 2 or 4 nights extra. I also want Project
to find out what happens when the Duration is changed so these figures
change: no weekends or 3 weekends, etc.
Any suggestion (outside VBA)?
Thanks
Situation: an engineer works on a task for 8 days. This means sometimes
there is one interim weekend and sometimes there may be two, depending on the
starting day of the week.
Problem: This task has to be charged 8+2 or 8+4 hotel nights.
I tried creating a material or a cost Task and could not do it. They don't
have calendars. By creating a special calendar to include weekends as working
days, the engineer gets charge 16 hours for the weekend which is not the
case. Also, by creating a Hammock task across the 8 days, material got
charged on working days. If I tried elapsed time (with or without the
Hammock) everything goes crazy.
I am left with entering the nights by hand which is silly. I want it to
automatically find out whether it is 2 or 4 nights extra. I also want Project
to find out what happens when the Duration is changed so these figures
change: no weekends or 3 weekends, etc.
Any suggestion (outside VBA)?
Thanks