N
Nickster
Hi,
When I bid a project, I provide a fixed hourly cost. However, I may need to
subcontract some functions to different experts at different hourly rates. I
need Project Professional to maintain my cost to these experts as well as the
project cost for my client based on the fixed hourly rate. How do I set it
up project server to provide both costs?
Thank you,
Nick
When I bid a project, I provide a fixed hourly cost. However, I may need to
subcontract some functions to different experts at different hourly rates. I
need Project Professional to maintain my cost to these experts as well as the
project cost for my client based on the fixed hourly rate. How do I set it
up project server to provide both costs?
Thank you,
Nick