check baseline

  • Thread starter Alexander Barvinsky
  • Start date
A

Alexander Barvinsky

Greetings,
In my company pm's very often forgot to save baseline before track project.
How to automate checking "is baseline saved" before publishing project on
server?

Thanks
Alerxander Barvinsky
pm4pm.org
 
E

Ed Morrison

Alexander,
Check to see if ActiveProject.BaselineSavedDate(pjBaseline) is a valid date.
Unfortunately, there is not an event such as BeforePublish. You could put a
reminder in on the application event ProjectBeforeClose.
 