I have a checked out enterprise calendar, how can I find out who checked
out? Is it possible to force it to be checked in?

Cheng Wu
 
D

Dale Howard [MVP]

Cheng Wu --

Log into PWA with administrator permissions and then click Server Settings -
Force Check-In Enterprise Objects. Click the pick list at the top and
choose the Enterprise Calendars item. On this page, you will now see who
checked out the calendar and when they checked it out. And then you can
also check in the calendar as well. Hope this helps.
 
W

Wu, Cheng

Thank you, it works well!
Dale Howard said:
Cheng Wu --

Log into PWA with administrator permissions and then click Server
Settings - Force Check-In Enterprise Objects. Click the pick list at the
top and choose the Enterprise Calendars item. On this page, you will now
see who checked out the calendar and when they checked it out. And then
you can also check in the calendar as well. Hope this helps.
 