A
andy
Hi -I am using 2003 and have a plan that has 350 lines, i think its OK but we
have introduced a lot of constraints with start dates..
Is there a way of checking to see if there are additional conflict errors in
the plan.
I am getting some conflict statements but when i check them and press the
"cancel" they go away. if i then close the project without saving and re open
it i dont see the conflict anymore. so i have no idea if the plan is robust
andy
have introduced a lot of constraints with start dates..
Is there a way of checking to see if there are additional conflict errors in
the plan.
I am getting some conflict statements but when i check them and press the
"cancel" they go away. if i then close the project without saving and re open
it i dont see the conflict anymore. so i have no idea if the plan is robust
andy