stevio
I want to be able to systematically update my project enterprise 2007
resource pool with vacation information that I get from HR in an Excel
spreadsheet.
Using VBA from within project pro 2007, how do I
1) checkout a given resource (by name) such that I can edit the resource
calander?
2) check it back into the enterprise resource pool?
I've got this all to work OK if I manually open the resource pool, select
the resources, check them out etc but broke my 20 minute rule on how to do
this systematically (If I can't work it out in 20 mins I ask for help on a
forum!).
Thanks,
Stevio
resource pool with vacation information that I get from HR in an Excel
spreadsheet.
Using VBA from within project pro 2007, how do I
1) checkout a given resource (by name) such that I can edit the resource
calander?
2) check it back into the enterprise resource pool?
I've got this all to work OK if I manually open the resource pool, select
the resources, check them out etc but broke my 20 minute rule on how to do
this systematically (If I can't work it out in 20 mins I ask for help on a
forum!).
Thanks,
Stevio