G
Greg
Is there any way to have subtasks _not_ drive the start and end date of their
summary task? Such as having all the subtasks be milestones?
Here's what I'm trying to accomplish from a big picture view:
We have a web application that has a very scaled-down project schedule
manager for home builders. We provide two "outline levels" (that's what MS
Project calls them) in our schedule: Phase and Task. The Phases are the
outermost summary tasks, and Tasks are subtasks to Phases. Phases derive
their start and end date from their subtasks (like MS Project).
In addition to these two outline levels, we provide a third level of
"Checklist Items". These items are _almost_ subtasks to Tasks, but have no
start date, end date, or duration. They are simply a list of information to
remind the builder of all the things that need to be complete for the Task to
be considered complete. There are some other bits of business logic
surrounding this, but essentially, that's it. Checklist Items are tasks
without start or end date and without duration.
In MS Project, I noticed that if I define a third outline level of tasks,
the second outline level tasks become "summary tasks", which means I cannot
control their start and end dates directly. I can only affect the deepest
outline level tasks (level 3, in this case).
So, after all that explanation, I'll restate my question: Is there a way in
MS Project to have "checklist items" that have no duration and that do not
directly control their summary task's start and end date?
Thanks very much!
summary task? Such as having all the subtasks be milestones?
Here's what I'm trying to accomplish from a big picture view:
We have a web application that has a very scaled-down project schedule
manager for home builders. We provide two "outline levels" (that's what MS
Project calls them) in our schedule: Phase and Task. The Phases are the
outermost summary tasks, and Tasks are subtasks to Phases. Phases derive
their start and end date from their subtasks (like MS Project).
In addition to these two outline levels, we provide a third level of
"Checklist Items". These items are _almost_ subtasks to Tasks, but have no
start date, end date, or duration. They are simply a list of information to
remind the builder of all the things that need to be complete for the Task to
be considered complete. There are some other bits of business logic
surrounding this, but essentially, that's it. Checklist Items are tasks
without start or end date and without duration.
In MS Project, I noticed that if I define a third outline level of tasks,
the second outline level tasks become "summary tasks", which means I cannot
control their start and end dates directly. I can only affect the deepest
outline level tasks (level 3, in this case).
So, after all that explanation, I'll restate my question: Is there a way in
MS Project to have "checklist items" that have no duration and that do not
directly control their summary task's start and end date?
Thanks very much!